title: "The plan package"
author: "Dan Kelley"
date: "`r Sys.Date()`"
output:
  rmarkdown::html_vignette:
    toc: true
    number_sections: true
    fig_caption: yes
    fig_width: 5
    fig_height: 5
    dpi: 72
    dev.args: list(pointsize=11)

vignette: >
  %\VignetteIndexEntry{The plan package}
  %\VignetteEngine{knitr::rmarkdown}
  %\VignetteEncoding{UTF-8}
---
<!-- edit vignettes/plan.Rmd then run with -->
<!-- devtools::build_vignettes() -->
<!-- in the console. -->

```{r, echo = FALSE}
knitr::opts_chunk$set(collapse = TRUE, comment = "#>")
```

**Abstract.** The `plan` package provides functions for planning and
describing projects and monitoring the progress towards completions of
individual tasks within projects.

# Introduction

This package provides (mainly graphical) tools for the planning of projects.
This is an early version of the package, providing support for burn-down
charts and Gantt diagrams.


# Burn-down charts

Burndown charts^[https://en.wikipedia.org/wiki/Burndown_chart] are used to
display a time series of the progress towards the goals of a project.  The
format is simple.  The x axis represents time, ranging from the onset of the
project to the deadline for completion.  The y axis represents the remaining
effort that is require to accomplish the work. As the work is carried out, the
chart provides a running summary of progress towards the deadline.  If work is
proceeding smoothly according to schedule, the chart takes the form of a
triangle, with the remaining effort falling from its initial value to zero at
the deadline. For guidance, a gray line is drawn to indicate this ideal
situation. If work is being accomplished faster than expected, the data will
lie below this gray line. However, if the project is falling behind schedule,
the data line will lie above the ideal line.  Thus, a glance at the chart
indicates whether the deadline can be met.  In most cases, the work is divided
into sub-tasks, and the remaining effort in each task is shown with a different
colour in the chart. This is helpful in identifying tasks that may need more
attention.

The following plots a sample burndown chart; replace the `data()` call with a
`read.burndown()` call, to create a chart of your own.

```{r}
library("plan")
data(burndown)
plot(burndown)
```

# Gantt charts

Gantt diagrams^[https://en.wikipedia.org/wiki/Gantt_Chart] indicate a timetable
for completion of the components of a project. The sample dataset `gantt` is a
hypothetical research plan for an MSc project; you can see how it is graphed
with `example(plot.gantt)`, or by entering the following code.
```{r fig.height=4, fig.width=6, dev.args=list(pointsize=10)}
library("plan")
data(gantt)
plot(gantt)
```

Moving beyond this built-in dataset, note that there are 3 main ways to create
`gantt-class` objects: (a) write information in a text file and use
`read.gantt()`, (b) use `as.gantt()` to assemble the object in one (somewhat
complicated) step, or (c) use `new()` to create an object and then
`ganttAddTask()` to add tasks one by one. The third approach may be the easiest
for beginners, so it is illustrated below, with a sketch of a typical
oceanography MSc program. Note that a legend is added, along with an indication
of the time at which the graph was prepared.


```{r fig.height=4, fig.width=6, dev.args=list(pointsize=10)}
library("plan")
g <- new("gantt")
g <- ganttAddTask(g, "Courses") # no times, so a heading
g <- ganttAddTask(g, "Physical Oceanography", "2016-09-03", "2016-12-05", done=100)
g <- ganttAddTask(g, "Chemistry Oceanography", "2016-09-03", "2016-12-05", done=100)
g <- ganttAddTask(g, "Fluid Dynamics", "2016-09-03", "2016-12-05", done=100)
g <- ganttAddTask(g, "Biological Oceanography", "2017-01-03", "2017-04-05")
g <- ganttAddTask(g, "Geological Oceanography", "2017-01-03", "2017-04-05")
g <- ganttAddTask(g, "Time-series Analysis", "2017-01-03", "2017-04-05")
g <- ganttAddTask(g, "Research") # no times, so a heading
g <- ganttAddTask(g, "Literature review", "2016-09-03", "2017-02-01", done=20)
g <- ganttAddTask(g, "Develop analysis skills", "2016-09-03", "2017-08-01", done=30)
g <- ganttAddTask(g, "Thesis work", "2016-10-01", "2018-04-01")
g <- ganttAddTask(g, "Defend thesis proposal", "2017-05-01", "2017-06-01")
g <- ganttAddTask(g, "Write papers & thesis", "2017-03-01", "2018-04-01")
g <- ganttAddTask(g, "Defend thesis", "2018-05-01", "2018-05-15")
font <- ifelse(is.na(g[["start"]]), 2, 1)
plot(g, ylabel=list(font=font),
     event.time="2017-01-01", event.label="Report Date")
par(lend="square") # default is round
legend("topright", pch=22, pt.cex=2, pt.bg=gray(c(0.3, 0.9)),
       border="black", xpd=NA,
       legend=c("Completed", "Not Yet Done"), title="MSc plan", bg="white")
```